Overland Bridge Construction Updated 6/3/10

What work will be done?
Complete painting of architectural metal railing on the east bridge sidewalk.
Open east bridge sidewalk to pedestrians.
Restripe Overland Avenue between National Place and National Boulevard.
Place K-rail on the west side of the bridge and close west sidewalk to pedestrians.
Complete reconstruct of Freeway eastbound off-ramp shoulder.
Demolish Freeway median west of the bridge and excavate for new foundation.
Clear, grub, and excavate for new foundation west of bridge abutments.

Where is the work occurring?
Along I-10 Freeway and along Overland Avenue Bridge.

When will work begin and end?
The work is continuing through the end of June 2010.

What time will crews be working?
The majority of the work will be performed between 7:00 a.m. and 4:00 p.m., Monday through Friday, excluding holidays.
Limited work that requires partial freeway lane closure will be performed between 7:00 p.m. and 6:00 a.m. the next morning, Monday through Friday, excluding holidays and rain days.
Caltrans will only allow partial freeway lane and ramp closures between 11:00 p.m. and 6:00 a.m. the next morning.

What can I expect?
Temporary Freeway lane and ramp closures between 11:00 p.m. and 6:00 a.m. the next morning (at least one through lane on the Freeway in each direction will be open during that time).

Will local access be impacted?
Yes, during the Freeway ramp temporary closure overnight.

Safety Measures
The west bridge sidewalk will be closed to pedestrians between National Blvd. and National Place during construction. K-railing will be installed along the west side of the bridge to protect the public and the construction crew. A few freeway lanes below the bridge will be temporary closed overnight to protect the public and construction crew. K-railing and crash cushions are installed along the Freeway median, eastbound off-ramp, and westbound on-ramp to protect the public and construction crew.

Who can I call regarding this notice?
City of Los Angeles Public Works, Public Affairs Office (213) 978-0333.
Tonya Durrell

DWP Substation Construction Update

Work has been delayed due to “procurement problems” with items needed for completion. They plan to restart work in February and March and complete the substation mid-April. We’ve also been told that they will re-pave the front sidewalk and hopefully, the alley. We’ll keep you posted if we hear of any changes.